All that can go wrong during a simple renovation.

Contact us - feedback is most welcome! A Homeowner's Journal Gallery of construction photos Code violations cited by Professional Engineers Disclaimer Recent developments

SNAFU Major

The Big Sag

 

Neither the project manager, general contractor nor framer seemed to give much thought to the architect's structural plans requiring post and beam supports for the new second floor.  The architect and building inspector, for their parts, did not seem to notice the oversight either. The result was a 3/4 inch sag at the center of the house five months into construction. 

Second floor central landing listing one inch over four feet.

In February, six weeks after receiving a scathing Engineer's Report, MyHome finally installed the first floor posts and the house was jacked up from the basement.  The main basement support, however, was not reinforced to the building inspector's specifications, and by May the center basement beams again sank back to a 1/2 inch sag.  Seven months later the second floor landing had sagged a full inch (photos, below).

Level on second floor landing showing one inch sag towards right.  Right end of level marks main stress point from roof to first floor.

Project supervised by MyHome Renovation (Project Manager), Trevor Spearman (Spearman Architectural Design) and Michael Palmentiero (Touch Of Class Home Improvements)

Project supervised by MyHome Renovation (Project Manager), Trevor Spearman (Spearman Architectural Design) and Michael Palmentiero (Touch Of Class Home Improvements)

    

 

Framing Plan F1 dated July 9, 2008 showing position of five first-floor structural posts.

Post were not installed until Feb. 12, 2009, seven months after second floor addition in place.

 

{Click any image to enlarge}

 

 

 

Project supervised by MyHome Renovation (Project Manager), Trevor Spearman (Spearman Architectural Design) and Michael Palmentiero (Touch Of Class Home Improvements)

 

Post schedule describing "P-3" as three 2x4s lag-bolted together. 

No lag bolts were used once the supports were eventually installed.

 

Project supervised by MyHome Renovation (Project Manager), Trevor Spearman (Spearman Architectural Design) and Michael Palmentiero (Touch Of Class Home Improvements)

 

    

 

Section showing plan for basement supports.

Seven month delay resulted in existing beams (in green) sinking 1/2 inch.

"Solid blocking under load-bearing posts" (in brown) never installed.

 

 

Project supervised by MyHome Renovation (Project Manager), Trevor Spearman (Spearman Architectural Design) and Michael Palmentiero (Touch Of Class Home Improvements)

 

Feb. 12 - Existing main beams resting on crumbling cement block column. 

Architect never provided plans for addressing crumbling column.

Angle in gap between beams shows effects of additional weight from new second floor.  

 

Work supervised or performed by MyHome Renovation (Project Manager), Michael Palmentiero (Touch Of Class Home Improvements) and Trevor Spearman (Spearman Architectural Design).

 

Feb. 12 - One of two weather-damaged LVL beams "sistered" to original main beams. 

 

 

Work supervised or performed by MyHome Renovation (Project Manager), Michael Palmentiero (Touch Of Class Home Improvements) and Trevor Spearman (Spearman Architectural Design).

 

Feb. 12 - LVLs used to reinforce basement beam (as shown in blue in drawing, above)  had been resting on dirt and were exposed to weather all fall and winter.

 

 

Work supervised or performed by MyHome Renovation (Project Manager), Michael Palmentiero (Touch Of Class Home Improvements) and Trevor Spearman (Spearman Architectural Design).

 

Work supervised or performed by MyHome Renovation (Project Manager), Michael Palmentiero (Touch Of Class Home Improvements) and Trevor Spearman (Spearman Architectural Design).

May 19 letter from Pelham Village Building Inspector documenting sag in basement beam after attempts by MyHome to repair in Feb.  

Click here for first page of letter documenting Architect's failure to provide detailed plans. 

 

 

Feb. 12 - No "Solid blocking under load-bearing posts" between existing basement rafters (top right of photo). 

Need for blocking shown in brown on Architect's section for basement supports, above.

 

 

Work supervised or performed by MyHome Renovation (Project Manager), Michael Palmentiero (Touch Of Class Home Improvements) and Trevor Spearman (Spearman Architectural Design).