{Click
on any photo to enlarge}
|
Gallery
of Construction Photographs
|
|
SNAFU
Major
The
Rain
The
Big Sag
The
Vapor Barrier
Inside
Out
The
Shake-down
The
Mold
The
"Promise"
SNAFU
Minor
The
Chimney
Exposed
Beams
Raised
Eyebrow
The
Roofline
The
Shingles
The
French Door Jambs
The
Live Wire
The
Radiators
The
Furnace
And
More...
Bright
Spots
The
Drawing
Copper
The
Concerned Sub
A
Touch of Irony
The
Letter
|
July
17, 2008 - Demolition started. Premises vacated for six weeks
of demolition and framing.
|
|
July
30, 2008 - Rafters
in place. Header beam on dormer slanting down to the right.
|
|
Major
framing complete except for eyebrow window and chimney extension.
Aug.
4, 2008
|
|
|
Chimney extension
installed (left), preventing green tarp from covering dormer and front
bedrooms.
Aug. 11, 2008
|
|
|
Remnants
of Aug. 15 thunderstorm - rainwater, filtered through the first floor ceiling, collects in the dining room light fixture.
Aug.
16, 2008
|
|
|
Staining on living room
ceiling one
day after the 1.3 inch deluge of rainwater.
Aug.
16, 2008
|

|
|
Same area
after eight more months of water exposure.
Apr.
14, 2009
|
|
|
Collapse
of second
floor bathroom ceiling due to weight of rain-soaked insulation
and sheet rock.
Aug.
17, 2008
|
|
|
Feltex
and tar paper finally applied to roof.
Original
incorrect lumber order sitting in front yard since July 25.
Aug.
18, 2008
|

|
|
Eyebrow
window as constructed vs. architect's plan (paper cut-out).
Aug.
27, 2008
|
|
|
Rain-soaked
insulation under warped floorboards on second floor.
May
20, 2009
|
|
|
Mold
growing on a soiled facemask left by workmen under bedroom
floorboards.
May
20, 2009
|

|
|
Installation
installed. No vapor barrier
(e.g. Tyvek) wrapping through window frames onto inside
walls.
Sept.
25, 2008
|

|
|
Eyebrow
framing corrected. Shingling
and copper flashing complete.
Rainwater continued to collect behind porch
and chimney flashing for more than 170 days.
Sept.
21, 2008
|

|
|
North
elevation - area exposed between original first floor stucco and OSB
siding for over 261 days.
Oct.
26, 2008
|

|
|
Water-damaged
stucco on south side of house. Rain and melted snow filtered into first
floor dining room, kitchen and bath for 158 days.
Oct.
28, 2008
|

|
|
Large
tarp covering unfinished wall from mid-Dec. to Feb. House was
supposedly "weather tight" as of Sept. 21, before autumn
and winter storms.
Stucco
work suspended from Jan. 4 to Feb. 3 due to freezing temperatures.
Jan.
7, 2009
|

|
|
Ice
and snow collecting behind first floor wall (north side).
Jan.
11, 2009
|

|
|
Workmen
applying stone and cement to middle section of chimney in 17 degree F.
temperatures.
Jan.
14, 2009
|

|
|
Beams
on crumbling basement support showing partial collapse from new
addition's weight.
Feb.
11, 2009
|

|
|
Water
stains and mold growth on first floor living room ceiling.
Mold
specialist hired by Project Manager on Jan. 20 declined to test the
entire first floor.
Apr.
14, 2009
|

|
|
Day after
general contractor's and project manager's final visit to site. Felt paper
falling off chimney extension. Rough stucco on East, South
and West walls. North wall OSB still exposed.
Apr.
18, 2009
|

|
|
|
|